• Existing cedar decking and all original framing removed and disposed of
  • Rotten joists and built up soil cleared out from under the deck footprint
  • Existing sloped concrete pad retained rather than broken out and hauled away
  • New treated framing set on low profile footings and vinyl shims, clear of soil and concrete
  • New cedar decking laid across the full footprint including the extended section
  • Boards fixed with a hidden fastener system driven at 45 degrees through the board edge
  • No screw heads across the deck surface and no face holes for water to sit in
  • Consistent board spacing and alignment maintained across the full run
  • Original scope reassessed on site once the decking came off and the framing was visible
  • Full framing removal explained and approved by the client before further demolition started
  • Concrete removal presented as a priced option rather than assumed into the scope
  • Constrained details around the sloped slab identified before the rebuild, not after
  • Neighbouring deck extended under the same mobilisation at the owner’s request
  • Staining scheduled on that deck so the new boards blend into the existing weathered cedar
  • River rock walkway and paving stone work scheduled as a follow-up on the same site