Every strata corporation in Metro Vancouver with five or more lots needs an electrical planning report by December 31, 2026. Many councils are still booking theirs.
The report itself is prepared by an electrical professional. What it leads to is construction work: electrical room upgrades, EV charging, new circuits and the patching, framing and finishing that come with them. This guide covers what the requirement is, who can prepare the report, and how to plan the work that follows.
An electrical planning report (EPR) is an assessment of a building’s electrical system. It shows how much capacity the building has today and how much it will need for future demands such as EV charging and heat pumps.
Under BC’s strata regulations, the report must include:
  • Current capacity of the building’s electrical system.
  • A list of existing electrical demands.
  • An estimate of peak demand and spare capacity.
  • An estimate of the capacity needed for future demands, such as EV charging and heat pumps.
  • Recommendations for managing and reducing demand.
Once complete, the EPR becomes a permanent record. It must be disclosed on a Form B Information Certificate when an owner or buyer requests one.
Metro Vancouver, Fraser Valley, Capital Region
December 31, 2026
Strata corporations with five or more lots. Islands reachable only by air or boat, such as Bowen Island, are excluded from this date.
New stratas
Five years after the plan is deposited
Newer buildings have five years from the deposit of the strata plan.
Everywhere else in BC
December 31, 2028
Strata corporations with five or more lots outside those regions, including Bowen Island and the Southern Gulf Islands.
Smaller stratas
Not required
Strata corporations with fewer than five lots do not need an EPR.
Only designated BC professionals can prepare an EPR, and it depends on the type of building.
  • Larger buildings (Part 3). Professional engineers or licensees registered with Engineers and Geoscientists BC, or applied science technologists and certified technicians registered with ASTTBC.
  • Smaller buildings (Part 9). All of the above, plus journeypersons in the construction or industrial electrician trade. Part 9 buildings are generally three storeys or less with a footprint of 600 square metres or less.
If council is unsure which category the building falls into, the local government can confirm it.
The EPR can be paid for from the operating budget, approved by majority vote at the AGM, or from the contingency reserve fund by a majority vote resolution at a general meeting. That majority vote also covers spending from the reserve fund on EV charging infrastructure and electricity management.
Most other reserve fund spending still needs a 3/4 vote, so it is worth knowing which category each piece of follow-up work falls into before the meeting.
The EPR is a plan, not a project. Once council has it, the next steps usually look like this:
1. Read the recommendations with your electrical consultant
Separate what is urgent from what is planning for the next ten years. Not every recommendation needs to happen right away.
2. Line it up with the depreciation report
Electrical items often overlap with other work already in the depreciation report. A parkade upgrade, a common area refresh or suite renovations can share access and disruption with the electrical work.
3. Get the construction side priced
Electrical upgrades in an occupied building involve more than the electrician. Opening and closing walls and ceilings, fire stopping, patching, painting and parkade work all need to be scoped and priced. A general contractor can coordinate the trades and give council one price.
4. Decide what goes to owners and when
Use the report and the pricing to decide what goes into next year’s budget, what comes from the reserve fund and what needs its own vote.
  • Who coordinates the trades? The electrical contractor, the general contractor or council?
  • How will residents be affected? Power shutdowns, noise and access to parkades and electrical rooms.
  • What finishing work is included? Patching, painting and fire stopping should be in the scope, not added later.
  • Can it be combined with other work? Grouping projects saves mobilization costs and disruption.
  • What permits are needed? Electrical permits are pulled by the licensed electrical contractor.
Have your EPR back?
We coordinate the construction work that follows the report and give your council one written price.
Or call directly
Phalanx Construction coordinates building upgrades for strata councils across North Vancouver, West Vancouver and Vancouver. We work alongside your electrical consultant and contractor, handle the construction scope around them, and keep residents informed.
Opening and closing walls, patching, painting, fire stopping and common area finishing are handled by one crew under one written scope.