If you sit on a strata council in Metro Vancouver, you now have a depreciation report. As of July 1, 2026, holding a current one is no longer optional for strata corporations with five or more lots, and the waiver that previously let councils vote to skip it is gone.
So the report exists. It runs to a hundred pages or more, it lists every major component in the building, and it projects when each one needs replacing and roughly what that will cost.
What it does not do is tell you how to actually get the work done. That is a separate step, and it is the one most councils find harder than commissioning the report itself.
What changed on July 1, 2026
Three things moved at once, and they interact.
Depreciation reports are now mandatory
For strata corporations with five or more lots in Metro Vancouver, Fraser Valley and the Capital Regional District, on a five year renewal cycle.
The waiver was removed
Councils can no longer vote by three-quarter majority to defer the requirement.
The minimum contingency reserve fund contribution rose from 5% to 10%
Measured against the annual operating budget.
The combined effect is that councils now have a professionally documented list of upcoming work, a legal obligation to keep it current, and a legally mandated funding stream sized against it. The pressure has shifted from whether to plan for the work to how to execute it.
Confirm the specifics that apply to your strata with your strata management company, since regional application and timing vary.
A depreciation report is not a construction scope
This is the distinction that trips councils up, and it is worth being precise about.
A depreciation report is prepared by a qualified professional who assesses the condition of building components and models their replacement over 30 years. It is a financial planning document. Its purpose is to answer how much money the strata needs to set aside and when.
A construction scope answers a different question: what specifically gets built, by whom, in what order, at what price, under what conditions.
A report line item might read something like “corridor finishes, remaining service life 3 years, estimated replacement cost $180,000.” That number came from a cost model, not from anyone walking your corridors with a tape measure and pricing your actual conditions.
Between that line and a contractor starting work sits a series of decisions the report does not make for you:
- What is actually included? Flooring only, or lighting, paint, doors and millwork as well?
- Does everything get done at once, or phased by floor?
- What happens to resident access while it is underway?
- Is the projected cost still accurate against current pricing and current site conditions?
- Does any part of it require an alteration agreement or a specific approval under your bylaws?
Turning a line item into a real job
Here is the sequence that works, in the order it works in.
1. Sort the report by urgency, not by cost
The largest number in the report is rarely the most urgent item. Something with two years of remaining service life and a moderate cost usually needs a decision sooner than a major component eight years out. Start by separating what needs a decision this budget year from what needs monitoring.
2. Group work that shares access
This is where councils save real money and almost always miss it.
If corridor flooring and corridor lighting are both due within a few years of each other, doing them together means one mobilisation, one round of resident disruption, one set of protection and cleanup. Split across two projects, you pay the setup cost twice and disrupt residents twice.
Look across the report for items that share a location, share access, or share a trade, and consider bundling them even where the projected years differ.
3. Get the work walked and priced against actual conditions
The cost figures in a depreciation report are estimates produced by a model. They are appropriate for financial planning and they are not quotes.
Before a council makes a funding decision, the work should be walked by a contractor who prices what is actually there. Existing conditions, access constraints, and what is behind the finishes all move the number, sometimes substantially in either direction.
Most contractors will do this walkthrough at no cost. Phalanx does, and we provide a budgetary scope document councils can take into an AGM or a special levy discussion, with no obligation attached.
More on how this work is scoped, quoted and sequenced: strata renovation contractor in North Vancouver.
4. Decide how it gets funded
Contingency reserve fund, special levy, or a combination. That decision belongs to the council and the ownership, but it is far easier to make with a real number attached than with a range from a 30 year model.
5. Confirm what needs approval
Depending on your bylaws and on whether the work touches common property or individual strata lots, some items may require an alteration agreement or a specific ownership vote. Confirm this with your strata management company before scoping, not after quoting.
6. Sequence it around the building
Occupied buildings have constraints that determine both cost and duration: noise-restricted hours, elevator booking, shared loading access, and residents who need to know what is happening on their floor and when.
A contractor who plans for those constraints before day one prices them into the schedule. One who does not will negotiate them mid-project, and that is where timelines slip.
What to ask a contractor at this stage
You are not buying a renovation yet. You are buying clarity on what the renovation would be. The questions that matter:
- Have you worked in occupied strata buildings before, and can you describe how you sequenced it?
- How do you handle noise restrictions and elevator access?
- Will you provide one written quote across the full scope, or separate trades?
- How are change orders documented and approved?
- Can you provide budgetary numbers we can use for AGM planning?
- Are you licensed, WorkSafeBC covered, and carrying liability insurance, with documentation?
Working through a report?
We walk the building and provide a budgetary scope document your council can take into an AGM. No cost, no obligation.
Or call directly
778-840-2215
Call or text, same day response
The practical next step
If your council is working through a current report and trying to decide what moves first, the most useful thing you can do before an AGM is get the priority items walked and priced against real conditions.
Phalanx handles strata common area renovation, suite work and multi-unit programs across North Vancouver, West Vancouver and the North Shore. We will walk your building and provide a budgetary scope document at no cost, whether or not the work ends up being ours.