Kitchens and bathrooms are where most condo renovations start, and where most strata problems start too. Both rooms involve water, drains, ventilation and noise, all of which affect your neighbours and the building.
This guide covers what you can usually change in a condo kitchen or bathroom in Vancouver and North Vancouver, what typically needs strata approval, and the details that decide whether the project runs smoothly.
What you can usually change, and what needs approval
Every building is different, so your own bylaws and renovation rules always come first. As a general guide:
Usually straightforward
Same layout, new finishes
New cabinets and countertops in the same footprint, new fixtures in the same location, paint, backsplash and lighting on existing circuits. Many stratas still want to be notified, and building work hours apply.
Usually needs approval and a permit
Moving plumbing
Moving a sink, toilet, shower or dishwasher. In concrete buildings, drains often run through the slab into the unit below, which makes relocation complex.
Usually needs approval
Flooring
Replacing carpet or vinyl with tile or hard flooring. Most bylaws set a minimum sound rating for the underlay to protect the unit below.
Usually needs approval
Ventilation and exterior
Changing a range hood or bathroom fan that vents through an exterior wall. The exterior is common property, so the strata decides.
Condo bathroom renovations: what to plan for
Bathrooms carry the most risk in a strata building because water travels.
- Waterproofing. A properly waterproofed shower and floor protects the unit below. Ask your contractor which waterproofing system they use.
- Drains and risers. The pipes behind the wall may serve other units. Shutting off a riser needs to be booked with the building.
- Tub to shower conversions. Popular, but they often involve drain changes and need strata approval.
- Exhaust fans. A new fan should connect to the existing duct unless the strata approves a change.
- Insurance deductibles. Many strata bylaws let the strata charge an owner the insurance deductible if a leak starts in their unit. Good workmanship is the best protection.
Condo kitchen renovations: what to plan for
- Keep the layout if you can. Moving the sink or dishwasher means moving drains and supply lines, which adds approvals, permits and cost.
- Check electrical capacity. New appliances, induction cooktops and extra circuits draw more power. Many stratas are completing electrical planning reports in 2026, and some limit what owners can add.
- Range hood venting. Recirculating hoods avoid exterior changes. A new exterior vent needs strata approval.
- Countertop delivery. Large slabs need to fit in the elevator or be carried in. Book the elevator and confirm sizes before ordering.
- Gas lines. Any gas work needs a licensed gas fitter, a permit and usually strata approval.
The approval and timeline
For work that needs approval, expect the process to look like this:
Scope and drawings
Your contractor prepares a written scope, layout and product list for the strata application.
Strata approval
Many councils meet monthly, so allow four to six weeks. Some stratas will ask you to sign an alteration agreement.
Permits
Plumbing, electrical and gas work need permits from the City of Vancouver, the City of North Vancouver or the District of North Vancouver, depending on where the building is.
Ordering
Cabinets and countertops often take several weeks. Order once approval is in hand.
Construction
A typical condo bathroom takes two to four weeks of work. A kitchen takes four to six. Building work hours, elevator access and inspections all affect the timeline.
Common mistakes to avoid
- Starting before approval. Councils can stop the work, charge fines and require it to be undone.
- Ignoring the flooring bylaw. The wrong underlay can mean replacing a brand new floor.
- Assuming the pipes are yours. Some pipes inside your walls belong to the building.
- Ordering before the scope is final. Changes after approval can mean applying again.
- Choosing a contractor with no strata experience. Building rules affect every day of the job.
Planning a condo kitchen or bath?
We prepare the scope for your strata application and work within your building’s rules from day one.
Or call directly
778-840-2215
Call or text, same day response
How Phalanx Handles Condo Kitchens and Baths
Phalanx Construction renovates condo kitchens and bathrooms in strata buildings across Vancouver and the North Shore, including the West End, Kitsilano, North Vancouver and West Vancouver. We prepare the written scope your strata needs and schedule the work around your building’s rules.
Demo, tile, waterproofing, cabinets, fixtures, flooring and finishing are handled by one crew under one scope, with licensed trades for plumbing, electrical and gas.